Massachusetts DG Collaborative

Change Requests Review Page

  This page lists all Change Requests received.  This list will appear in Table 2 of the 2006 Report.  The final versions of these Change Requests, stating how each was resolved, are also incorporated into Attachment C of the 2006 Report (submitted to the DTE in June 2006). 

   Please note that the Tariff itself -- in Attachments A and B -- is the authoritative version of the recommendations of the DG Collaborative, and is available at:

    http://masstech.org/dg/collab-reports.htm

 

2006 Change Requests (Final Versions, pdf)

Date Submitted

  • Feb. 16, 2006
  • John DaSilva, Aegis Energy Services
  • March 3 , 2006
  • John Bzura, National Grid
  • March 2, 2006
  • Colleen Gusmano, WMECo
  • March 3 , 2006
  • Dave Doucette, Energy Program Consulting, and
  • Mike Jacobs, AWEA
  • March 6, 2006
  • Joseph Feraci, NSTAR
  • March 7, 2006
  • Gerry Bingham, Fran Cummings
  • March 7, 2006
  • Bingham, Rabinowitz, Cummings
8: Process for selection of multiple interconnection procedures such as DTE Tariff, ISO-NE Smalll Gen (Final)
  • March 8, 2006
  • Gerry Bingham
  • March 7, 2006
  • SEBANE

10: Remove requirement of an external disconnect switch for Simplified (Final, with explanation for withdrawal)

  • March 1, 2006
  • Rui F. Afonso, Climate Energy
  • March 1, 2006
  • Rui F. Afonso, Climate Energy

12: Require Company to complete System Modifications on a timely basis and to inform Customer of progress (Final)

  • March 13, 2006
  • George Aronsen, CommonWealth Resource Management Corporation (CRMC)
  • March 13, 2006
  • George Aronsen, CRMC

14: Clarify exemption of net metering (up to 60 KW) from insurance requirements (Final)

  • March 14, 2006
  • DOER, SEBANE, MTC, DCAM, GSA, DHCD
  • March 20, 2006
  • John Bonazoli, FG&E

16: Eliminate the 10 kW limit for Simplified Network Interconnection, but retain limit of 1/15 of the customer’s minimum load, with change to daytime load in the case of solar (Final)

  • April 3, 2006
  • SEBANE
  • April 7, 2006
  • Cummings (on behalf of sub-group on insurance and indemnification)
  • April 10, 2006
  • Gundlach, MA Department of Correction

19: Extend self insurance option to entities that are not "companies" (Final)

  • Aprl 25, 2006
  • DCAM
  • May 26, 2006
  • agreed upon by multiple parties

 

   

2005 Change Requests

Date Last Updated

Massachusetts Electric (Tim Roughan)
Change Request 2
June 7, 2005
Division of Energy Resources (Gerry Bingham)
Change Request | Redlined Letter
June 7, 2005
Ingersoll-Rand (Jim Watts)
Change Request | Redlined Tariff
June 7, 2005
June 7, 2005
Massachusetts Electric (Tim Roughan)
Change Request
June 7, 2005
Turbosteam Corporation (Sean Casten)
Change Request | Redlined Letter | Redlined Tariff
June 7, 2005
Western Mass Electric (Cindy Janke)
Change Request
June 7, 2005

Massachusetts Electric (John Bzura)
Change Request |Redlined Tariff

June 7, 2005